[Systers-dev] Biweekly status report(ORM)

kanika vats kanika.krikan at gmail.com
Sun Jun 28 11:11:14 PDT 2009


Hi,
My Biweekly status report is as follows:
Last two weeks I have been busy with testing my ORM code for DlistUtils
trying to make it run error free.I have problems in commiting my code to my
feature branch in launchpad as my bzr is giving some strange errors.The part
of the code that sets up the isolation level is still left to be figured out
with storm implementation.I had contacted the storm people but there are
still some issues that need to be resolved but thit is not important at
present as code is running perfectly fine without it.I had decided my
Mid-term goals with my mentor which was to provide a running orm code for
systers mailman DlistUtils.py . I hope to check-in the code by this coming
week so it can be evaluated and tested,also I intend to remove the bugs
found in it by 6th of july.It is after this that I will work on improving
the structure of DistUtils.py making it more readable,understandable
properly structured and documented.
-- 